Overview
- The last external supply line, the 750 kV Dneprovskaya link, was damaged on September 23, leaving the plant in cold shutdown and relying on emergency diesel generators.
- Director Yuri Chernichuk says a nuclear-safety risk persists but staff maintain control of critical functions, citing ample cooling water reserves and sufficient fuel stocks.
- Two of roughly 20 diesel generators that were under repair are being finished and are expected back on standby duty within hours, according to station management.
- Station specialists say they are ready to repair the damaged line but cannot safely reach the site due to continued shelling in the contact zone and are requesting a quiet period for work.
- At the Valdai forum, President Vladimir Putin accused Ukrainian forces of striking areas around the facility, said the reactor itself has not been hit, referenced IAEA presence, and noted this is about the tenth such incident since the war began.