- The intersection at Wuhlheide was reopened to one-way car traffic on June 6 as structural removal work continues.
- Tram services beneath the former bridge have been running since May 29 after a brief suspension during the initial demolition phase.
- Verkehrsinformationszentrale Berlin reports that all demolition and debris clearance will conclude by June 27.
- Left turns from Rummelsburger Straße into Treskowallee remain prohibited, with drivers directed along a signed detour via Blockdammweg and Ehrlichstraße.
- City planners plan to replace the bridge with a redesigned structure aimed at reducing congestion and bolstering public transport capacity.