Overview
- Engineers completed multi-day static and dynamic trials in late August, using a dense sensor network to track stress, vibration and deflection across the span.
 - Testing included a convoy on August 25 and separate runs using up to 96 trucks totaling more than 3,000 tons, according to outlets covering the program.
 - Project teams reported normal performance during the trials, with calibration and monitoring scheduled to continue through September.
 - The opening window remains unsettled, with some reports citing late September and others pointing to the end of October pending Chinese Ministry of Transport approval.
 - The bridge extends about 2,980 meters with a 1,420-meter main span and towers reaching 332 meters, completed in roughly three years at a reported cost near $283 million.