- The EPSAR-led project was confirmed on site by regional environment chief Vicente Martínez Mus after preliminary works started this week.
- The new facility is designed to treat up to 600 m³ per day, three times the current capacity, to meet regulatory performance standards.
- The execution period is estimated at 16 months, with completion targeted after the build that begins in October.
- A compact, reusable modular plant will maintain wastewater treatment throughout construction to avoid service interruptions.
- Upgrades include full sludge management, a terrestrial emissary to change the discharge point, and a carbon filter to reduce odors, with municipal land ceded to enable the works.