Overview
- Three 92‑meter heavy transports carrying roughly 80‑meter rotor blades became stuck in an S‑curve at the B176 town entrance, halting traffic overnight.
- Police alerted Mayor Maik Kunze, and municipal crews removed streetlights, signs, and advertising boards; one tree was felled, and no additional trees were ultimately required.
- After about 24 hours, the convoy continued to Windpark Langendorf, where large mobile cranes lifted the blades off the trailers on Wednesday.
- The deliveries serve a project adding five very large turbines reported at about 250 meters tall with 162‑meter rotors, underscoring the logistical challenges on local roads.