- Caltrans began a planned 55‑hour operation that started Friday night to reduce the eastbound 91 between SR‑241 and Green River Road from seven lanes to three.
- The lane reductions produced multi‑mile backups and hours‑long delays that spilled onto surface streets and prompted some drivers to cancel plans.
- Several motorists reported fewer than the promised three lanes were open at times and that the paid FasTrak express lane was closed during the work.
- Caltrans recommended detours using the 57 to the 60 or Carbon Canyon and says the closure is set to end at 5 a.m. Monday with the same restrictions scheduled for next weekend.
- The $6 million culvert replacement is intended to improve drainage and add wildlife passage, and Caltrans says the concentrated weekend approach shortens total work time while compressing short‑term disruption.