Watchdog Finds Irregular Payments and Delays at Castillo Forga Restoration in Arequipa

The audit’s findings prompted corrective recommendations for the regional tourism executing unit.

Overview

  • In a simultaneous control report, the Contraloría identified three core issues, including valuation of unbuilt provisional fencing that risks paying for work not performed.
  • Required air quality and noise monitoring was not carried out at the start of the project as specified, undermining planned environmental controls.
  • The project, launched on September 23, recorded 0.41% progress in its first week versus 0.95% planned, triggering calls for an accelerated schedule and potential penalties.
  • Inspections on October 9–10 found the resident engineer and several contractor specialists absent, raising risks to technical oversight and work quality.
  • The work is executed by Aro Constructora y Mineros EIRL under a contract exceeding S/25 million, and the findings arrive as the regional governor reports delays across nine works tied to conflicts in site committees.