Regional authorities say the three‑hectare site had no valid permit, prompting an immediate stop to enforce local building and environmental rules.

Overview

  • Wallonia issued a stop order after inspectors said the build covered about three hectares and that no proper building permit exists for the Farciennes site.
  • Google told AFP it suspended work in compliance with local instructions and is waiting for further guidance from regional regulators.
  • Greenpeace prompted the intervention by filing an emergency procedure after drone footage in November showed substantial construction progress despite permit disputes.
  • Google won an initial permit in 2024 but applied this year to expand the footprint and to use water from the Sambre river for cooling instead of the originally planned air cooling.
  • The Belgian action follows similar European scrutiny of large data centres, including Finnish stops in October, and raises local concerns about heavy water and power use on a former mining site near Charleroi.