Overview
- València Sud station is being rebuilt on a one-meter-high base to shield the new vestibule from future floods.
- Renovations include three elevators, ramps and a step-free pedestrian tunnel linking extended platforms to a 506-space parking area with 14 accessible spots.
- The new Barranc del Poyo bridge between Paiporta and Picanya has passed its load test, marking a major safety milestone.
- Ten kilometers of new track have been installed and electrification tests are underway on the València Sud–Torrent section.
- The Metrovalencia control center will relocate to the first floor and full service restoration for the l’Horta and la Ribera lines is slated for June 21 pending final safety checks.