Overview
- The €12 million contract was awarded to Acciona Construcción S.A. in September 2023 under an original 18-month schedule now extended to the first quarter of 2026
- Out of 18 hospital structures, only the last large building remains as most modules were dismantled after work began in October 2024
- Authorities confirm that all asbestos-containing materials were removed in advance following statutory safety procedures
- Comprehensive safety plans are protecting workers and onsite services, including emergency medical teams and a health center, throughout the demolition
- Residents have voiced worries over persistent dust and smoke clouds but officials insist rigorous controls mitigate any health risks