Vaishnaw Confirms 2027 SuratBilimora Launch as First Turnout Installed on MumbaiAhmedabad Bullet Train

Engineers are introducing vibration‑absorbing components with composite sleepers to enable stable operation at 320 km/h.

Overview

  • Railway Minister Ashwini Vaishnaw inspected works in Surat and said the first 50 km SuratBilimora stretch is slated to open in 2027.
  • He set targets of 2028 for ThaneAhmedabad and 2029 for full MumbaiAhmedabad operations across the 508 km corridor.
  • The first turnout was installed at the under‑construction Surat station during the visit, marking a key trackwork milestone.
  • New track systems include roller bearings, vibration‑mitigation mechanisms and composite sleepers to maintain stability at high speeds.
  • Officials cited a 320 km/h design speed on the main line, 80 km/h on loop lines, and an end‑to‑end journey time of about two hours seven minutes.