USS John F. Kennedy Completes Navy Acceptance Trials, Keeps Spring 2027 Delivery Target

The milestone clears a formal Navy verification step that allows Navy‑led testing to start as contractors finish remaining weapons‑elevator and arresting‑gear work.

Overview

  • The carrier, which completed Acceptance Trials on Saturday, Aug. 15, returned to the shipyard and moved into Preliminary Acceptance so the Navy can begin its own underway tests.
  • Acceptance Trials are run by the Navy’s Board of Inspection and Survey to verify propulsion, navigation, aviation operations, combat systems, damage control and habitability before formal delivery.
  • Program officials say Kennedy is about 98 percent complete and remains on track for delivery in spring/March 2027, but unresolved Advanced Weapons Elevator installations and Advanced Arresting Gear certification still pose schedule and readiness risk.
  • The ship’s procurement cost is reported at roughly $13.2 billion, and the Navy plans an initial Norfolk operating period followed by a 2029 move to Naval Base Kitsap where about $145 million in electrical upgrades are underway.
  • The Ford‑class program’s new high‑power systems have driven repeated delays, which have strained the single U.S. carrier yard’s capacity and prompted the Navy to delay retirements of older carriers to maintain force levels.