Overview
- The Air Force and Northrop Grumman finished a four-month Pathfinder logistics exercise that culminated in an inert LGM‑35A being stacked and de‑stacked at Vandenberg on Sept. 14, 2026.
- The 719th Test Squadron and Northrop completed the first flight-test Critical Design Review, which officials say confirms the missile’s design maturity and that hardware testing meets requirements for a 2027 test launch.
- Pathfinder tested nationwide transport, specialized vehicles, mobile cranes and pad interfaces to prove crews can safely move and assemble full missile sections on a launch pad.
- The program is still under a Pentagon-ordered restructure after major cost growth and a Nunn‑McCurdy notification, and Milestone B recertification plus final cost and schedule decisions remain unresolved.
- Sentinel is designed to replace the Minuteman III, involves more than 500 industry partners and a workforce of about 10,000, and aims for initial capability in the early 2030s if the 2027 flight test and recertification succeed.