Overview
- Acta 333 creates a three‑month binational working group to evaluate a submarine outfall and the expansion of the San Antonio de los Buenos plant from 18.26 MGD to 43.37 MGD.
- A sedimentation basin at Smuggler’s Gulch is slated for completion before the 2026–2027 rainy season to curb cross‑border pollution.
- The agreement schedules construction of the Tecolote–La Gloria wastewater plant with 3 MGD capacity by December 2028.
- NADBank will establish an operations and maintenance account with recommendations due in 12 months, structured to avoid additional U.S. taxpayer funding.
- Implementation begins immediately with joint monitoring, after the accord was signed in Tijuana under the July MOU’s year‑end deadline and entered into force.