Particle.news
Download on the App Store

UK Grid Operator Axes ‘Zombie’ Projects, Sets 283GW Pipeline With 2030–2035 Targets

The shift to a first‑ready system aims to accelerate clean power toward 2030 goals.

Overview

  • Developers are being notified today whether their projects are dropped or prioritized for grid connections by 2030 or 2035.
  • More than half of the roughly 700GW queue has been removed, with projects totaling over 300GW canceled to clear space for viable schemes.
  • Neso replaces the queue with a 283GW delivery pipeline, assigning 132GW for delivery by 2030 and 151GW by 2035.
  • For 2030 connections, nearly half the capacity is expected from solar and batteries, about a third from onshore and offshore wind, and roughly 3% from gas-fired power.
  • Neso has separately assessed large consumers such as data centers, with about 99GW of applications fast-tracked, and the reforms are expected to unlock roughly £40bn of investment.