UK Energy Operator Says Faster Net Zero Path Adds £350bn, Prompting Government Pushback

Ministers call the modelling illustrative, with NESO itself highlighting exclusions and uncertainty.

Overview

  • NESO compared a rapid pathway aligned with Ed Miliband’s clean‑power plans and the CCC’s 7th carbon budget to a slower route that falls short of the 2050 target.
  • The operator’s analysis estimates the faster route would cost about £350bn more than the slower path, framed by critics as roughly £14bn a year or about £500 per household if the target were dropped.
  • Additional costs are concentrated in the next decade, with premiums above £40bn in some years, and the rapid pathway becoming cheaper only from around 2046.
  • NESO cautioned its scenarios are not the cheapest way to reach net zero and exclude carbon pricing, with outcomes highly sensitive to future fuel prices and technology rollout; DESNZ rejected the figures as not reflecting true transition costs.
  • Across pathways, NESO projects total energy system spending falling from roughly 10% of GDP today to about 5–6% by 2050, and it notes a shift from imported fuels toward domestic renewables, networks and electric heating with potential jobs and health benefits.