Particle.news

Two Minnesota Cities Move to Tighten Controls on New Data Centers

The actions could slow proposed projects by adding new local approvals and prompting broader review of energy and water impacts.

Overview

  • Last week the Minneapolis City Council approved a compromise ordinance that bars data centers as a building’s primary use, limits them to existing buildings, and requires council approval for any new downtown data center.
  • Minneapolis Mayor Jacob Frey must act on a possible veto by Nov. 19 and the city's six-month moratorium on data centers is set to expire on Nov. 21.
  • Downtown business leaders led by Adam Duininck urged the mayor to veto the ordinance, saying the extra council-approval step will add time and risk that could deter investment and jeopardize projects.
  • In St. Cloud the City Council rejected proposed siting rules and voted 4-3 to pursue a one-year moratorium, scheduling a public hearing and possible vote for Dec. 21 after residents raised concerns about noise, water use, energy demand, and tax breaks.
  • City officials note downtown Minneapolis already hosts about eight data centers and Xcel Energy has signaled interest in more projects while St. Cloud offers ample water, power and land but has received no formal hyperscale proposals so far.