TTC Expansion Hits Crunch Point as Crosstown Testing Pauses and Finch West Nears Debut

A TTC board update details operational handoffs with Metrolinx alongside signalling work required for seamless openings.

Overview

  • Metrolinx began a Revenue Service Demonstration on Line 5 in October, then paused testing after an Oct. 16 yard collision at Mount Dennis.
  • Officials now say Crosstown vehicles could begin limited running next month, though no full opening date has been confirmed.
  • The Finch West LRT (future Line 6) entered its demonstration phase in September and is expected to launch in 2025, with a Dec. 7 date reported as an unconfirmed rumour.
  • The Scarborough Subway Extension is tunnelling, with the TTC preparing Line 2 for opening through an automatic train control procurement and fleet planning.
  • Major projects advance in parallel: the Yonge North tunnels contract was awarded in August, Ontario Line operations are being defined toward a 2031 target, ECWE station and systems work was contracted in August, and the Eglinton East and Waterfront East LRTs await firm funding.