Trump’s Border Wall Push Lags With 619 Miles Still Unbuilt

State refusals to grant access paired with court injunctions threaten to push completion past President Trump’s term.

Overview

  • Customs and Border Protection data from Nov. 10 show about 619 miles of primary wall remain unbuilt along the U.S.‑Mexico border.
  • Construction has sped up from roughly 2.6 to 3.9 miles per week between mid‑June and early November but that pace projects completion in late 2029, after President Trump leaves office.
  • The administration faces mounting legal friction, including more than six lawsuits in West Texas and individual eminent‑domain filings that already include a case against a New Mexico church.
  • Officials in Texas have used administrative tools to halt work, with the General Land Office issuing a July cease‑and‑desist and the newly elected land commissioner saying the state will prefer surveillance technology over a physical wall on state land.
  • If timelines hold, the effort will require either a dramatic surge in building, broader land access through contested eminent‑domain rulings, or a shift to technology‑based enforcement, and nearby communities in Big Bend worry about lasting harm to parks, ranches and ecotourism.