Overview
- The ministry has formalized the services contract, enabling the UTE ANTEA–META–INGE consortium to begin work.
- The scope covers geological and geotechnical field campaigns and the drafting of a complementary informative study adapted to current regulations.
- The dossier addresses a technically complex corridor, with hydrogeology highlighted as a critical challenge between Ourense, Pontevedra and Vigo.
- Officials say the plan moves next to public information, with local reporting indicating a February submission target and a 24‑month delivery timeline.
- Construction remains distant, with local projections pointing to an earliest 2030 start, about €3 billion in works, and roughly 45 minutes saved on Vigo–Madrid journeys.