- Transnet ran a two-day technical trial that moved a 696-wagon freight formation about 7.6 kilometres in length over roughly 860 kilometres, the company reported.
- The convoy operated on the Saldanha Bay–Northern Cape corridor and carried empty wagons because the exercise was designed to test train handling rather than commercial hauling.
- Locomotives were placed along the train and controlled by Radio Distributed Power, a radio system that times traction and braking inputs to reduce forces between wagons during starts, stops and grade changes.
- Transnet says the formation exceeded the 2001 BHP Australian mark by about 247 metres and 14 wagons, but independent homologation of a new world record has not yet been confirmed.
- Company officials say the test will guide changes to traction, braking and circulation practices that could raise mineral export capacity from inland mines to Saldanha Bay and lower transport costs if proven safe and reliable.