- A disconnection of the 500 kV Jurupari/Oriximiná C1 and C2 transmission lines triggered the event on Thursday and caused widespread outages in Manaus, all municipalities of Roraima, and parts of western Pará.
- The Operador Nacional do Sistema Elétrico (ONS) said about 2,027 MW of load was interrupted, with roughly 1,719 MW in Manaus and 308 MW in Roraima.
- Protective schemes known as the Esquema Regional de Alívio de Carga (ERAC) automatically shed supply and left about 110,000 customers without power in seven municipalities of western Pará, Equatorial reported.
- Restoration proceeded in stages with recomposition beginning in the late afternoon and concessionaires reporting normalization milestones, including Equatorial saying Pará loads were back by 18:01 and Âmbar announcing full restoration in Amazonas at 19:15.
- ONS and the national regulator Aneel are investigating the root cause and the sequence of events, and regulators have noted conflicting timestamps between concessionaire and ONS reports while consumers are urged to use official service channels for any remaining outages.