Particle.news

Track Settlement Forces Single‑Line Running on Lumding–Badarpur Hill Section

Night curbs plus single‑line operations raise the risk of delays to passenger movement and essential goods to northeastern states

Overview

  • The settlement of soil beneath two tracks near New Harangajao left Lines 1 and 2 out of service after heavy monsoon rain, with the damage estimated at about 300 metres and reported on Thursday, July 30.
  • All train movements have been shifted to the remaining Line 3 under strict monitoring and safety checks, and passenger trains are banned through the affected stretch between 7 p.m. and 5 a.m.
  • Restoration teams and heavy machinery have been deployed on a war footing to rebuild the sunken section while work continues under weather constraints.
  • Northeast Frontier Railway has extended six pairs of special trains (12 services) to ease disruption, including additional weekly DibrugarhKolkata runs through August and a revised Rangiya timing for the KolkataDibrugarh special from August 3.
  • The disruption has caused cancellations, long delays for travelers such as the detained Kanchanjunga Express, and creates a risk of interrupted deliveries of food, fuel and construction materials to Tripura, Mizoram, Manipur and southern Assam.