Overview
- Technical inspections found severe structural damage near the Poyo and l'Horteta ravines, with several dwellings at imminent risk of collapse.
- The operation is budgeted at €471,296, covering demolition, debris removal, project drafting, site management, and safety coordination.
- Work will start in the urban core and then extend to dispersed areas, prioritizing properties that pose the greatest danger to public safety.
- Contracts were processed under the emergency procedure in the Public Sector Contracts Law, with monthly certifications and regulated waste management.
- The programme is slated to run for roughly three months with strict health and safety measures to protect workers and residents.