Toronto’s Gardiner Expressway Stretch Set to Reopen by Oct. 27 After Accelerated Repairs

Ontario says $73 million for 24/7 work cut the schedule by roughly half.

Overview

  • All lanes between Dufferin Street and Strachan Avenue are expected to be open by the end of October, with officials signaling a target as early as Oct. 27.
  • Crews replaced a 700‑metre section of concrete deck and girders in a project that began in March 2024 and was originally slated to run until April 2027.
  • Transportation Minister Prabmeet Sarkaria credits around‑the‑clock construction funded by the province for finishing well ahead of the revised timeline.
  • The province assumed responsibility for the Gardiner and the Don Valley Parkway two years ago, a shift that enabled the acceleration funding and approach.
  • Officials acknowledge heavy congestion during the work and say lessons from this project could be applied to speed up other road repairs, with four more Gardiner sections still to come.