Thuringia Suedlink Section Cleared for Construction With October Start

Regulatory sign-off clears underground-cable construction on the GerstungenMellrichstadt route, a key step toward delivering the 700-kilometre link by 2028.

Overview

  • The Bundesnetzagentur has approved the roughly 75-kilometre corridor from Gerstungen in Thuringia to Mellrichstadt in Bavaria, enabling work on this Suedlink tranche.
  • TransnetBW says preparatory activity is underway and the official start is scheduled for Monday, with sites and drill pads being set up in several municipalities.
  • Cables will be installed underground in ducts with horizontal drilling used for road and water crossings, with trenching and drilling planned through 2027 before cables are pulled.
  • Adjacent segments in Bavaria and Hesse are already under construction, and TenneT reports progress including about 2,000 metres of tunnel built for the Elbe crossing.
  • The joint TransnetBW/TenneT project is designed for around 4 gigawatts to move northern wind power south, targets completion by late 2028, and TransnetBW estimates its share of costs at about €8.5 billion.