Overview
- The first trial run covered roughly 10 km between Cadbury Junction and Kasarvadavali, with Chief Minister Devendra Fadnavis and Deputy Chief Minister Eknath Shinde inspecting the priority stretch.
- Lines 4 and 4A together span 35.2 km with 32 elevated stations and eight-coach trains, supported by a 45-hectare depot under construction at Mogharpada for Lines 4, 4A, 10 and 11.
- MMRDA moves next to Independent Safety Assessor reviews and mandatory CMRS approvals before passenger service, with phase one targeted for December 2025.
- Leaders cited expectations of about 13–14 lakh daily riders initially and roughly 21 lakh after integration with Line 11 by 2027, alongside projected 50–75% cuts in travel time.
- Separately, the final 9 km of the fully underground Metro Line 3 is scheduled for inauguration by Prime Minister Narendra Modi on September 30, completing the 33.5 km Aqua Line from Aarey to Cuffe Parade.