TEPCO Inserts Robot Arm Into Fukushima Daiichi Unit 2 Containment

The months‑long insertion aims to map internal obstructions to guide a planned experimental molten‑fuel debris extraction next year.

Overview

  • TEPCO began inserting a folded remote robot arm through the containment‑side X‑6 penetration on Friday, October 2, 2026 to gather three‑dimensional interior data.
  • The arm is stored folded inside a metal “enclosure” and will be slowly extended into the vessel so cameras and 3D sensors can survey confined, high‑radiation spaces.
  • Engineers will spend roughly three to four months cutting and removing obstacles such as steel rails using high‑pressure water jets before completing a full survey.
  • The work is planned as a phased, roughly six‑month campaign that will precede a third experimental attempt to sample molten fuel debris in 2027.
  • TEPCO says the remote operation both limits worker radiation exposure and will reduce technical uncertainty needed to plan future large‑scale debris retrieval during decommissioning.