Temporary Steel Framework Erected on Talacre Beach for HyNet CO₂ Cable Works

HyNet says the conspicuous beach setup is a short-term stage to install a trenchless conduit powering a link to its offshore carbon storage.

Overview

  • The steel supports on Talacre Beach enable assembly of an underground conduit for a combined electric and fibre‑optic cable serving the Point of Ayr terminal and the New Douglas Offshore CCS Platform.
  • HyNet schedules conduit installation between February and April 2026, with an offshore cable pull by vessel planned from June to August 2026.
  • A cofferdam made of temporary steel sheet piles is in place to contain drilling fluids and is due for removal after the current phase completes at the end of August 2026.
  • Horizontal directional drilling is being used to route the conduit beneath protected sand dunes without open trenching at the surface.
  • Public measures include a Point of Ayr footpath closure and site screens, and HyNet says all temporary equipment will be cleared after works as wider onshore pipeline preparations and community drop‑in events proceed.