Overview
- Chief Minister A. Revanth Reddy declared the deadline non-negotiable and ordered quarterly reviews to track progress.
- A Cabinet meeting will be convened before September 15 to secure pending approvals, with funds to flow through a green channel to prevent delays.
- Contractor JP Associates was told to mobilize all machinery immediately and will be held accountable for any slippage, with tunnelling to proceed from both ends.
- Targets call for roughly 175–178 meters of excavation per month and about 7 meters per day, with three regulated shifts to finish the remaining 8–9 km of the 44 km tunnel.
- Specialist support includes Singareni engineers, uninterrupted power for operations, an NGRI heli‑borne survey to map hazards, and safety measures such as enhanced ventilation and redundant systems.