Telangana HC Ramps Up Scrutiny in Sigachi Blast Case With Amicus and Probe Orders

Judges signaled readiness for court-monitored scrutiny to ensure accountability across regulatory agencies.

Overview

  • The Bench pressed the State to clearly explain the roles of the Factories, Labour, Provident Fund and other regulators responsible for enforcing compliance at the Sigachi unit.
  • Citing reports of excess inflammable material on-site, the court questioned inspection frequency and noted the last recorded inspection occurred in December 2024.
  • Investigating officer DSP Prabhakar appeared in person and was asked whether he faced any pressure, with the Bench offering to insulate the probe or assign a senior officer if required.
  • Judges directed the investigation to move against those deemed actively responsible or culpably negligent and warned that a court-monitored probe could follow if responsibility is not fixed.
  • Sigachi was ordered to file a detailed compensation affidavit and the State to provide FIR details for eight missing workers, as CBIC counsel Dominic Fernandes was appointed amicus and the case was listed for December 30.