Overview
- An independent engineering firm reported that CBTC upgrades on the F, A/C/E and G lines face delays of one to three years and have run millions over their initial budgets.
- The MTA board’s Capital Program Committee voted to modify Hitachi’s contract by $47 million to install 5G radios on R211 train cars so they can interface with modern signal systems.
- Federal Communications Commission sign-off on 5G equipment is still pending, delaying the start of system commissioning and service improvements.
- Officials blame obsolete 4G transceivers unsupported by Siemens and a shortage of qualified engineers for the prolonged schedule slippage.
- Revised completion targets now stand at September 2025 for the F line in Brooklyn, October 2027 for the A/C/E, March 2028 for the eastern Queens F line and July 2029 for the G line.