Stellantis Sues Unifor Over Blocked Access to Brampton Plant

The suit raises pressure over a disputed repayment demand tied to a 2022 retooling deal, potentially deciding whether the mid‑December sale is stopped.

Overview

  • Stellantis filed a statement of claim in Ontario Superior Court seeking an injunction that says Unifor blocked entrances with trucks and pylons and prevented Roshel’s environmental consultant Pinchin Ltd. from accessing the idled Brampton plant.
  • Unifor rejects those allegations and says its demonstrations are aimed at saving the jobs of roughly 2,000 laid‑off Brampton workers who have been off work since the plant was idled in 2023.
  • Federal Industry Minister Mélanie Joly described recent talks with Stellantis negotiators as productive and continues negotiations with Ontario and Unifor to try to reverse the sale and preserve jobs.
  • Ottawa has served Stellantis a notice of default under the 2022 retooling agreement and officials are disputing repayment terms reported at about C$831 million against Stellantis’ offer to return roughly C$24 million.
  • Roshel agreed to buy the plant and retained Pinchin to begin environmental work on Nov. 9, and the sale remains scheduled to close in mid‑December unless the parties reach a deal or a court ruling alters the transaction.