Overview
- BMRCL has begun placing steel girders to connect HSR Layout with BTM Layout over the Silk Board bottleneck.
- Officials now aim to open the final stretch by December 2025, with early 2026 as a fallback if work slips.
- A 42-metre segment switched from prestressed concrete to a steel girder to resolve a turning-radius constraint toward Electronics City.
- The schedule slipped from a planned September opening due to heavy surface traffic, limited night work windows, and design changes.
- A 5.5 km section from Ragigudda to Silk Board opened in November 2024, easing one direction of traffic, while commuters still report poor pedestrian links at the Silk Board Metro station.