Stade Floating LNG Terminal Commissioned and Begins Gas Injection

The facility is intended to boost short-term gas supplies as the fourth state-run floating import terminal completed under the federal build-out.

Overview

  • DET put the Stade floating LNG import terminal into operation and began feeding gas into the network on Monday, November 16, 2026.
  • Federal officials say the terminal could supply up to 3.2 billion cubic meters of gas to Germany in 2027, roughly the annual heating need of about 2.6 million four-person households.
  • The project opened after multi-year delays that saw the terminal ship Energos Force temporarily chartered abroad and then return to Stade in September 2026.
  • Environmental group Deutsche Umwelthilfe warned the new capacity risks deeper dependence on U.S. fracked gas and noted that Stade must use already crowded transmission pipelines, while a larger land-based terminal at Stade is permitted to run on fossil gas until the end of 2043.
  • Stade completes the federal programme of four state-run floating terminals that Germany built after the 2022 Russian invasion of Ukraine, a move that strengthens near-term supply diversity but raises concerns about locking in long-lived fossil infrastructure and its effect on the energy transition.