Spanish Utilities’ New Maps Show 83% of Distribution Nodes at Capacity

Utilities say the CNMC’s 6.46% return proposal would underfund distribution upgrades, putting new industrial and digital connections at risk.

Overview

  • For the first time, companies published CNMC‑mandated, node‑by‑node capacity maps on Tuesday.
  • The disclosure covers networks of Aelec members (Iberdrola, Endesa, EDP) and Naturgy, which together operate about 90% of Spain’s distribution grid.
  • The companies report that 83.4% of nodes are already saturated, preventing new connection requests at those points.
  • Utilities attribute the congestion to a surge in access requests and investment rules that have not matched concentrated demand growth.
  • They urge higher regulated returns of around 7.5% versus the CNMC’s 6.46% proposal and stricter planning to fund reinforcements needed for industry, renewables, data centers, housing, storage and electric mobility.