The petition moves to the nuclear regulator for a safety assessment under rules requiring no extra costs to consumers.

Overview

  • Iberdrola, Endesa and Naturgy filed the request after CNAT’s shareholders approved pursuing an extension of Almaraz’s operating licence.
  • Miteco confirmed receipt and will send the file to the Consejo de Seguridad Nuclear for the mandatory radiological‑safety opinion.
  • To meet legal deadlines, the owners are also submitting closure paperwork, so the CSN will work on both an extension case and a shutdown dossier in parallel.
  • The companies have shelved a prior demand for sweeping tax cuts to smooth approval, while the Government maintains conditions on safety, security of supply and zero added cost.
  • Extremadura’s president pressed for approval of the extension, as Minister Sara Aagesen withheld a stance pending the CSN’s review and emphasized the regulated process.