Overview
- Officials say a visible improvement should begin in 2027 after years of investment and upgrades following the Gelida crash on January 20, 2026.
- The ministry has spent emergency funds since Gelida, including up to €180 million for reinforcements and a broader €3,000 million of certified works during the current mandate.
- Signal upgrades known as ERTMS2 are being rolled out with a €280 million budget and already operate on the R1 (Maresme) line to boost safety, capacity and control-room visibility.
- Operational performance is being eroded now by thefts of copper cable, which numbered 35 in September and produced about 15,000 minutes of delay, and by new Alstom trains from Santa Perpètua de Mogoda that are delayed until spring.
- Short-term fixes such as a temporary third rail in Tarragona and the near-complete move to a joint control centre at Estació de França aim to improve coordination, while political moves seek tougher penalties for cable theft and a mixed company prepares the transfer of Rodalies competencies to the Generalitat.