Overview
- The Boletín Oficial del Estado published a ministerial order authorizing both Almaraz reactors to remain in service at least until 8 June 2030.
- The decision overrides previously scheduled shutdowns that had set Unit I to close in November 2027 and Unit II in October 2028.
- The ministry acted after the Consejo de Seguridad Nuclear gave technical clearance in mid‑July and the plant’s three owners formally requested an extension in October.
- Extending Almaraz is expected to force a revision of Spain’s staggered closure plan so Enresa can avoid overlapping dismantling work at Ascó I, Cofrentes and other sites.
- Any operation beyond 2030 will require unanimous agreement of all AIE partners or an authorised change of ownership, and fiscal demands over levies remain an outstanding political issue.