Overview
- The 158-hectare development is budgeted at 1.6 trillion MNT to deliver 8,565 homes.
- Foundation work has started on 82 of the 113 planned residential blocks for the Selbe sub-center.
- China Construction 6th Engineering Bureau holds the first-phase contract for about 4,362 units and pledges completion of building works by April 2, 2027, with 60–70% of workers Mongolian.
- Project leadership expects initial residents to move in by July 2027 and schools and kindergartens to open by autumn 2027.
- Weather briefings flag clear, light-wind conditions in Ulaanbaatar today near -3 to -5°C, brief snow and stronger winds around Nov 19 and 22, and a winter trending colder in northern regions and warmer in the southwest.