Overview
- San Antonio Abad on Metro Line 2 reopened to passengers on Sunday, June 7 after nearly three months of work that closed the station from March 17.
- The remodel added more than 500 LED luminaires, about 1,000 m² of porcelain tile, 750 m² of waterproofing, nearly 200 m² of marble and continuous access doors replacing turnstiles.
- Line 2 is running continuous service between Tasqueña and Cuatro Caminos but trains pass through Chabacano, Portales, Nativitas and Zócalo/Tenochtitlan without boarding or alighting.
- The program covers roughly 19–20 stations and is carried out by multiple contractors with Constructora Eina SA de CV named as the supervising firm in procurement records.
- Officials say phased reopenings will continue before the World Cup, passengers were supported by RTP buses during closures, and commuters should expect further temporary station work and service notices.