Overview
- The A13 north tube at the Tunnel de Saint‑Cloud was closed for major consolidation on Monday, November 16, with works scheduled to last about nine months and some reports setting an end date of August 31, 2027.
- Traffic on the first day was exceptional with regional congestion peaking around 430–440 km cumulés in the morning and remaining well above normal into the evening.
- Authorities say inspectors found extensive structural damage, including large fissures in places reportedly up to roughly 40 cm, and they estimate the reinforcement will cost about €35 million.
- To limit disruption officials opened two main diversion corridors, made the A14 free weekdays for Paris‑to‑Normandy traffic, issued a prefectoral order to block through‑traffic in small communes, and asked navigation apps to steer drivers to recommended routes.
- The closure affects about 80,000 daily users of the corridor and risks economic strain for local businesses while police and local councils enforce heavy‑vehicle routing and protect secondary streets from overflow traffic.