Overview
- RTS Operations told Singapore and Malaysian authorities on Oct. 2 that passenger services are now expected to begin in February 2027 after extra time is allowed for remaining works.
- All system tests and trial runs are scheduled to be completed by Dec. 31, 2026, after which an independent safety assessor must certify the system before regulators can grant permission to carry passengers.
- Physical works are largely finished: Woodlands North station is complete and Malaysia’s transport minister has said the Bukit Chagar side and rail infrastructure are finished, leaving integration and testing as the main tasks.
- The 4 km cross‑border link is designed for about a five‑minute trip and up to 10,000 passengers per hour each way, with co‑located customs and immigration at both stations and RTSO, a SMRT–Prasarana joint venture, holding the 30‑year concession.
- Transport experts warn February should be treated as a conditional target because an opening near Chinese New Year or Hari Raya could expose weaknesses in passenger flow and crowd management, so joint rehearsals and staffing readiness will be crucial.