Overview
- Attorneys general Peter Neronha and William Tong filed a motion in federal court in Providence seeking a preliminary injunction to lift the Trump administration’s August stop‑work order.
- Ørsted and its partner separately asked a D.C. judge for similar relief, with a preliminary hearing set for Sept. 22.
- The project is designed to deliver about 704 megawatts for roughly 350,000 homes, carries a Rhode Island Energy contract at 9.8 cents per kWh, and faces a key December 31, 2026 power‑delivery milestone.
- ISO New England warns the delay increases grid‑reliability risks and state filings project higher utility costs, including an estimated $500,000 a year for Connecticut starting in 2028 if the project does not proceed.
- The states argue irreparable harm from lost specialty vessels and up to 1,200 union jobs as the administration has not identified a legal violation behind its national‑security rationale, and a government response in the AGs’ case is due Oct. 1.