Report: Oracle to Power 1.4GW Texas AI Megasite With Gas Generators at $1 Billion a Year

The reported plan reflects a rush to bypass yearslong grid delays.

The West Texas site is located in Shackelford County.
Image
Image

Overview

  • Bloomberg, citing unnamed sources, reports Oracle will run a new West Texas data center on on-site gas generators at an annual operating cost exceeding $1 billion, and the company has not confirmed the plan.
  • The facility is located in Shackelford County near Abilene, is being developed by Vantage Data Centers, and is described as a roughly 1.4-gigawatt campus that would rank among the largest data centers globally.
  • Using generators is presented as a way to bring AI capacity online sooner rather than waiting years for a utility connection and new transmission infrastructure.
  • Oracle’s broader AI push includes a reported 4.5-gigawatt cloud pact tied to OpenAI’s Stargate project and large Nvidia chip clusters for accelerated computing.
  • Observers highlight potential air-pollution risks from gas turbines and note the company’s rapid buildout coincided with its first negative annual cash flow since 1990.