Overview
- Red Line operations remained thinned after a punishing week, following single‑track service near Ashmont and an estimated 17.5% of scheduled trains running by Wednesday night, with residual delays persisting.
- Multiple commuter rail lines reported new cancellations and lengthy delays because of equipment shortages and mechanical problems, with some riders shifted to shuttle buses and reduced parking at stations from snow removal.
- The MBTA attributed disruptions to snow, ice, and subzero wind chills affecting switches, engines, and train doors, and said teams were working around the clock to return vehicles to service.
- Older Red Line cars struggled in the cold, officials said, noting only six newer train sets are in service and a 252‑car replacement order is running years behind schedule.
- The agency canceled this weekend’s planned Red Line signal work due to lingering storm impacts and potential additional winter weather, and urged riders to allow extra travel time across the system.