Overview
- Preparatory work started Monday with the inbound ramp closed from 07:00 and the outbound ramp closing from 15:00.
- The city urges drivers to avoid the A14, with urban detours routed via Kirschweg and Leipziger Straße.
- On Tuesday, crews will lay a sand fallbed beneath the structure to catch debris and damp vibrations, protecting roads, sidewalks and underground lines.
- The demolition is slated to run October 20–25 during daytime hours, according to the city.
- After the bridge is removed, Magdeburger Ring traffic will use the existing ramps, Brenneckestraße will remain closed, and temporary bridges are planned for early November.