Railways Breaks Through 6.59‑km Tunnel on Rishikesh–Karnaprayag Line
The work validates specialised engineering used to stabilize loose Himalayan ground, advancing the project toward its December 2029 completion target.
Overview
- Tunnel‑14 was joined on Friday, Nov. 27, 2026, when crews linked a 4.7 km drive from Sumerpur with a 1.79 km drive from Marora to complete the 6.59 km bore.
- Engineers used targeted methods to manage unstable ground, including pre‑excavation and multi‑drifting under inhabited areas, 30–35 m micropiles, 15–20 m rock bolts, consolidation grouting, daytime controlled blasting near settlements, and long‑range ventilation for the 4.7 km drive.
- The ministry reports tunnel excavation is about 97% complete, overall physical progress near 79%, and the project cost estimated at roughly Rs 37,119 crore with full line opening targeted for December 2029.
- When finished the 125 km broad‑gauge line will cut Rishikesh–Karnaprayag travel from about 6–7 hours by road to roughly 2–2.5 hours by train, improving access for pilgrims, tourists and local communities.
- The breakthrough is a major step on a route that runs largely underground—about 80–85% in tunnels with some very long bores—and it reduces key engineering risks while shifting work toward final linings, systems installation and commissioning.