Overview
- The #QuieroCorredor movement gathered roughly 2,500–2,800 attendees at València’s Roig Arena for its last large business event, with Transport Minister Óscar Puente and other senior officials participating.
- The planned València central through-station still has no completed project, with the opening of the economic bids now set for 11 March 2026 for a €30.2 million design contract.
- Given the contract’s 48‑month term, a March 2026 start would place the nominal end of the design work around March 2030 before construction can proceed.
- Since 2018, the government reports more than €6.028 billion in awarded works and nearly €8 billion in tenders for the Mediterranean Corridor.
- The business platform is ending mass mobilizations but will continue semiannual progress checks and will channel part of its advocacy toward water management.