Push Trolley Inspection Clears Beleghata–IT Centre Stretch for Electrical Works

The engineering check paves the way for electrical fit-out that will allow signalling and trial runs to start before the section can carry passengers.

Overview

  • A push trolley inspection was successfully carried out on the Beleghata–IT Centre (Salt Lake) section on September 17, confirming track alignment and readiness for the next phase of work.
  • Metro officials say viaduct and ballastless track works on the third phase are complete, which permits crews to begin overhead and electrical installations on the stretch.
  • The third phase is described as substantially completed for civil and track work, but passenger service has not started because signalling, systems integration and trial runs remain to be done.
  • Opening this stretch will give commuters direct metro access to Salt Lake Sector V’s IT hub, shortening commutes and easing road congestion for workers traveling to New Town.
  • The 32 km Kavi SubhashJai Hind Bimanbandar Orange Line was sanctioned in 2010 and is being built in five phases; two earlier sections already carry passengers and the next project steps are electrical fit‑out, signalling and trial operations.